You Just Received a PIP. Here Is the Furniture Timeline That Actually Works
A Property Improvement Plan arrives as a document with a scope and a date on it. The scope is negotiable at the margins. The date usually is not.
Most owners start by asking what the furniture will cost. The better first question is when you need to have chosen a manufacturer, because in a PIP the calendar is what puts programs into trouble, not the price list.
Start from the deadline and work backward
Here is a realistic sequence for a guestroom and public space furniture package, counted backward from the date the brand expects the work finished.
| Weeks before deadline | What has to be done |
|---|---|
| 26 to 34 | Manufacturer shortlisted, scope and budget confirmed, quoting begun |
| 22 to 26 | Manufacturer selected, purchase order issued, deposit paid |
| 20 to 24 | Fabric and finish selections locked, COM ordered if applicable |
| 18 to 22 | Shop drawings approved, prototype or sample approved if required |
| 16 to 20 | Brand submission package sent, brand approval received |
| 6 to 16 | Production |
| 4 to 8 | Freight, delivery and warehousing |
| 2 to 6 | Installation, phased by floor or wing |
| 0 to 2 | Punch list, snag resolution, final walk |
Those bands overlap because real projects overlap. The point is the total: a domestic furniture program for a full-property PIP realistically needs six to eight months from first conversation to final installation. Imported programs need more, usually nine to twelve.
Industry guidance broadly agrees. Trade sources recommend engaging a furniture vendor six to nine months before the target installation date, during design development rather than after construction documents are issued.
Why the deadline is firmer than people assume
A PIP is issued by a franchisor under the franchise agreement. Deadlines typically run from six months to thirty six months depending on severity and asset category, and they are generated by one of three triggers: a franchise agreement coming up for renewal, a property changing hands and needing brand certification, or a quality assurance inspection score falling below a threshold, often around 80 out of 100.
Hilton PIPs generally run on six to eight year cycles and most allow twelve to eighteen months for completion, with milestone dates for design approval and construction commencement built into the schedule.
Missing the date is not a scheduling inconvenience. It puts the franchise relationship at risk, and brands have been noticeably less willing to extend since the post-pandemic deferral period ended. Between 2020 and 2022 owners successfully negotiated deferrals from most major brands because occupancy had collapsed and franchisors had no leverage. That window has closed, and the deferred work created a backlog estimated in the region of twelve to fifteen billion dollars that is now being executed across the industry at the same time. Manufacturer capacity is competitive in a way it was not five years ago.
The owners who get into trouble are rarely the ones who could not afford the furniture. They are the ones who started the conversation in month nine of a twelve month window.
The four stages where furniture programs slip
1. Fabric and finish approval
This is the single most common cause of delay, and it is almost always avoidable.
The sequence is: select fabric, confirm availability and lead time, order, receive, inspect, then cut. Each step has failure modes. The pattern is discontinued. The dye lot shifts. The mill quotes eight weeks on a fabric everyone assumed was in stock. The specified fabric turns out to be unsuitable for the piece it was assigned to.
If your package uses COM, the fabric clock and the production clock are two separate clocks and the slower one governs. Order fabric early, confirm yardage with the manufacturer before you buy, and request a cutting for approval so a dye lot problem surfaces before anything is cut rather than after.
2. Shop drawing and sample approval
Every custom piece needs drawings approved before production. Where a prototype or sample is required, add two to four weeks for build, ship, review and revision, and add the same again for each revision round.
Two rounds is normal. Four rounds means somebody was approving from a rendering instead of a physical sample, and it will cost you six weeks.
3. Brand submission
Brand approval is its own queue and it does not run on your timeline. Submission packages routinely come back with comments. Plan for at least one revision cycle and confirm at the outset exactly what the brand wants to see: drawings, specifications, physical samples, finish chips, or all four.
Ask the brand contact early whether the specification package in your PIP is current. Brand standards documents are large and sections written years ago survive revision cycles. This is where a clause calling for a superseded fire standard, for example, will usually turn up.
4. Freight, customs and installation labor
Domestic freight from a US factory to a US property is a known quantity, usually one to two weeks depending on distance and whether you are staging through a warehouse.
Ocean freight is not. Twelve to sixteen weeks is the planning number for an Asian sourced program, and that is before customs, before a port delay and before the possibility of a container being inspected. Add the current tariff environment and imported programs carry both a cost and a schedule risk that has to be priced into the decision.
Installation labor is the quiet one. Everybody plans for it and few people book it early enough. In a renovation wave, installers get busy at exactly the same time manufacturers do.
What to do if your window is already tight
If you are inside six months and the furniture is not ordered, the options narrow but they do not disappear.
Phase the scope. Brands will often accept a phased completion if you present a credible schedule showing the whole scope landing inside the deadline. Guestrooms first, public space second, is a common split. Get the phasing agreed in writing.
Reduce custom content. Every custom piece adds approval cycles. Where a standard model in a custom fabric will meet the brand standard, take it. You are trading a small amount of design distinctiveness for several weeks.
Choose domestic over imported. Four to six weeks of production plus a week or two of domestic freight is a fundamentally different schedule from twelve to sixteen weeks of ocean transit. In a compressed window this is often the deciding factor regardless of unit price.
Consider refurbishment where the brand allows it. If the frames are sound, reupholstery and cushion replacement can meet a brand standard at a fraction of the schedule and cost. This has to be confirmed with the brand before you commit, because it varies by brand and by the specific PIP line item.
Talk to the manufacturer about the real date, not a comfortable one. We can often compress production for a program that is properly specified and paid on time. We cannot compress a program where fabric selections are still open.
Phasing without closing floors
Most properties cannot go dark for a renovation, and most do not need to.
The standard approach is to take a block of rooms offline, complete them, return them to inventory and move to the next block. A commonly used pattern is sixteen rooms per block with two blocks in progress at any time, which keeps roughly thirty two rooms out of service. Schedule blocks during your lowest occupancy months and the revenue impact is usually manageable.
The furniture implication is that your delivery schedule has to match your block schedule. Delivering an entire property's worth of guestroom furniture at once means paying to warehouse most of it. Staged delivery against the installation calendar is nearly always cheaper, and it needs to be agreed with the manufacturer at order, not requested later.
What we need from you to quote a PIP package
To return a realistic timeline and price rather than a placeholder, we need:
- The PIP document, or at minimum the furniture line items and the completion deadline
- Room count and room types, plus the public space scope
- The brand and the specific brand standard package, if you have it
- Any specification requirements already fixed, including fire and fabric requirements
- Whether fabric will be COM or specified from our library
- Your target installation start date and whether the work will be phased
- Who has authority to approve drawings and samples, and how quickly they can turn a review
The last point matters more than it looks. The fastest programs we run are the ones with a single named decision maker who can approve a sample in two days. The slowest are the ones where every approval goes through a committee.
Frequently asked questions
How long does furniture take for a hotel PIP?
Plan on six to eight months from first conversation to final installation for a domestically manufactured program, and nine to twelve months for an imported one. Production itself is usually six to sixteen weeks. The rest is selection, approval, brand submission, freight and installation.
When should I start talking to a furniture manufacturer about a PIP?
As soon as you have the PIP document. Industry guidance is to engage a vendor six to nine months before the target installation date, during design development rather than after construction documents are issued.
What triggers a hotel PIP?
Usually one of three things: a franchise agreement coming up for renewal, a property sale where the incoming owner needs brand certification, or a brand quality assurance inspection score falling below a threshold, often around 80 out of 100. Brand standard updates can also trigger PIPs across a portfolio.
How long do I get to complete a PIP?
Deadlines typically range from six to thirty six months depending on severity and asset category. Hilton PIPs commonly allow twelve to eighteen months with milestone dates for design approval and construction commencement.
Can I renovate without closing the hotel?
Yes, and most properties do. The usual method is taking a block of rooms offline at a time, completing them and returning them to inventory before starting the next block. Your furniture delivery schedule needs to be staged to match the block schedule.
What causes the most delays in PIP furniture programs?
Fabric approval, sample and shop drawing revision rounds, brand submission queues, and freight. Fabric is the most common and the most avoidable.
Can reupholstery satisfy a PIP requirement?
Sometimes, depending on the brand and the specific line item. If the frames are structurally sound it can meet the standard at a fraction of the cost and schedule. Confirm with the brand in writing before committing.
What happens if I miss the deadline?
That is a matter between you and your franchisor under the franchise agreement, and the consequences vary. It is not a position you want to be in, and brands have been less willing to extend since the post-pandemic deferral period ended.
Working to a PIP deadline?
Send us the furniture line items and the completion date. We will come back within one business day with a timeline that hits your deadline, or tell you honestly if it cannot be done and what would need to change.
Last reviewed: September 2026. Timelines in this article are planning guidance based on typical programs. Your brand standard and PIP document govern. Confirm all deadlines and approval requirements with your franchisor.